Fervo reaches $11.9 billion in contracted geothermal revenue

Fervo expands contracted revenue as geothermal projects advance
Geothermal developer Fervo reported $11.9 billion in contracted revenue in its third-quarter earnings release, rising from $7.2 billion in the previous quarter. The increase comes as the company delivers early power projects and pursues large electricity contracts for hyperscale data-centre demand.
Fervo connected its first 100-megawatt power plant to the grid earlier this year. The facility is at Cape Station in Utah, where the company is also developing Cape Google 400, a 396 MW project for Google scheduled for completion by the end of 2028.
The scale of the Google agreement is reflected in Google’s Utah geothermal supply agreement, which outlines the 396 MW geothermal supply arrangement for Utah data centres and the project’s role in Google’s power planning.
Cape Station is designed for staged capacity additions
Fervo says Cape Station could generate 8.4 gigawatts of electricity, materially above the roughly 4 GW that experts had previously estimated for the site. Cape Google 400 will be grid-connected, allowing Google to take contracted electricity while retaining the option to sell power to other customers if its data-centre development is not ready.
Chief executive and co-founder Tim Latimer said this structure allows Fervo to build the generating project on its own schedule while Google develops a potential data centre on a separate timetable. That flexibility is tied to Fervo’s construction approach: it can bring groups of wells online in phases rather than waiting for one large generating facility to be completed.
Its newer wells are deeper and hotter, with each capable of producing 15 MW of gross power. Fervo combines several wells into a unit it calls a GeoBlock. The first completed GeoBlock generated 33 MW, while more recent units have reached 50 MW. The company says that size is intended to match demand from a typical data-centre hall, enabling capacity to be added as each block is completed.
Costs remain central to the commercial case
Fervo remains at an early commercial stage. It ended the quarter with an operating loss of $43.7 million, alongside $1.9 billion in cash and cash equivalents and $301.6 million in long-term debt.
The company reported that the first phase of Cape Station cost $7,000 per kilowatt of capacity. It put the cost of the Google project at $5,500 per kW. With subsidies, Fervo said that level is roughly equivalent to a new natural-gas plant using fuel priced at $6 per million BTUs.
Fervo’s longer-term target is $3,000 per kW, a level it says could undercut natural-gas power even at current gas prices. For businesses procuring power for expanding data-centre loads, the reported progress makes delivery milestones, grid arrangements and the company’s ability to reduce installed costs central factors in evaluating geothermal contracts.