Nebius Sets $40 Billion 2027 Buildout Plan Amid Microsoft Delay

Nebius Sets $40 Billion 2027 Buildout Plan Amid Microsoft Delay

Nebius has outlined planned 2027 capital expenditure of $40 billion to $45 billion as it expands AI computing capacity, while part of a major Microsoft deployment at a Vineland, New Jersey data center has slipped by months. The company said its contract with Microsoft is worth up to $19.4 billion, but only just over half of the relevant capacity is now expected by the end of the year; the remainder is planned for the second quarter of 2027.

The plan puts substantial weight on customer prepayments and financing backed by customer contracts. Nebius ended the third quarter with $7.4 billion in cash and said prepayments plus asset-backed financing of investment-grade contracts could fund up to 85% of its projected 2027 spend.

A funding model tied to delivery

Chief revenue officer Marc Boroditsky said Nebius received significant prepayments under agreements with Microsoft and Meta, before capacity was delivered. Chief financial officer Maria Del Dado Alonso Sanchez identified Microsoft and Meta among contracts that could support this financing approach. Boroditsky also said prepayments could be used for additional cash requirements.

The strategy makes project completion central to the economics of the expansion. Nebius said new deals signed during the third quarter included prepayments exceeding the cost of constructing the capacity behind them. It forecast 2027 revenue of $12 billion to $13 billion and said it expects to reach pre-tax break-even in the fourth quarter of that year.

Nebius reported third-quarter revenue of $981 million, a 571% increase from a year earlier, although roughly one-third came from a one-time payment linked to a new partnership model. It cut its 2026 revenue forecast by $200 million to $3 billion, citing delays at third-party sites including the New Jersey location.

New Jersey site faces operational and contractual pressure

Andrey Korolenko, Nebius’s chief product and infrastructure officer, said the delay followed DataOne’s decision to wind down temporary generation faster than expected as the facility transitions to Bloom Energy fuel cells. DataOne operates the site, rather than Nebius.

In August, Floodlight reported that at least 45 natural-gas generators were operating at the DataOne site without permits for gas-generator operations. New Jersey regulators later fined the facility $1.1 million, finding that the generator use violated federal law. DataOne also faces a lawsuit from nearby residents over an alleged constant humming noise from the data center.

Nebius’s summary of the Microsoft agreement says Microsoft may terminate affected service after a grace period if delivery dates are missed and no alternative capacity is provided. The contract also contains financial penalties for late delivery. Nebius said Microsoft has been involved in planning, but did not state whether Microsoft had accepted the revised dates.

What customers and operators should watch

Nebius says delays concern sites outside its control, while facilities it builds itself are arriving on time or ahead of schedule and are expected to supply most new capacity from 2027. The company’s earlier compute relationship with Reflection and Nebius compute agreement illustrates how demand for large-scale infrastructure can be linked to AI development plans, while this case highlights the importance of the physical delivery schedule.

For businesses buying or financing AI capacity, the practical implication is to examine who controls the site, the power transition, fallback capacity and remedies for missed milestones before relying on contracted compute availability.

#aicompute#cloudinfra#datacenters#nebius